THE METHODOLOGY
Our Proven Solar Journey
A transparent, structured process refined across hundreds of successful installations in Surat.
01
Site Survey & Consultation
1-2 DaysOur engineers inspect roof conditions, sun exposure, and energy usage so the system is sized correctly from day one.
Roof structural analysis
Shadow mapping and sun path study
Energy consumption audit
Customized system proposal
02
System Design & Quotation
2-3 DaysYou receive a clear plan with component details, projected savings, and transparent costing.
System visualization
Component specification sheet
Detailed cost breakdown
Long-term savings projection
03
Approvals & Documentation
7-10 DaysWe manage utility paperwork and subsidy documentation to keep the process smooth and compliant.
Net metering application
Building permission support
Subsidy registration
Insurance documentation
04
Installation & Testing
3-5 DaysOur trained crew installs modules, wiring, and inverters with strict safety and quality checks.
Module mounting and alignment
Inverter and electrical setup
AC/DC safety configuration
Testing and commissioning
05
Grid Connection & Go-Live
5-7 DaysAfter inspections and meter setup, your system starts producing power and we guide you on monitoring.
Net meter installation
Final inspection clearance
Monitoring app setup
Warranty activation
Total Timeline: 3-4 Weeks
From initial briefing to first power generation, we keep the execution fast, clear, and accountable.
Consultation
Same Day
Design
2-3 Days
Approvals
7-10 Days
Installation
3-5 Days