The Methodology

Our Proven Solar Journey

A transparent, structured process refined across hundreds of successful installations in Surat.

01

Site Survey & Consultation

1-2 Days

Our engineers inspect roof conditions, sun exposure, and energy usage so the system is sized correctly from day one.

Roof structural analysis
Shadow mapping and sun path study
Energy consumption audit
Customized system proposal
02

System Design & Quotation

2-3 Days

You receive a clear plan with component details, projected savings, and transparent costing.

System visualization
Component specification sheet
Detailed cost breakdown
Long-term savings projection
03

Approvals & Documentation

7-10 Days

We manage utility paperwork and subsidy documentation to keep the process smooth and compliant.

Net metering application
Building permission support
Subsidy registration
Insurance documentation
04

Installation & Testing

3-5 Days

Our trained crew installs modules, wiring, and inverters with strict safety and quality checks.

Module mounting and alignment
Inverter and electrical setup
AC/DC safety configuration
Testing and commissioning
05

Grid Connection & Go-Live

5-7 Days

After inspections and meter setup, your system starts producing power and we guide you on monitoring.

Net meter installation
Final inspection clearance
Monitoring app setup
Warranty activation

Total Operational Timeline: 3-4 Weeks

From initial briefing to first power generation, we keep the execution fast, clear, and accountable.